In order to commence the renovations of the existing permanent school buildings, the management was looking for a temporary solution for 8 classrooms for 4 years.
In consultation with the school management, the municipality and the fire department, a building was developed that suited the available site.
During the month of August, Symobo installed the classrooms and connected the utilities.
The teachers were able to start the lesson on September 1. A kiss from the teacher and a bench ahead!
“The teachers were able to start the lesson on September 1. A kiss from the teacher and a bank ahead!”